Look-ahead and master schedule: 3WLA alongside Primavera P6 and Microsoft Project

    Primavera P6 and Microsoft Project are critical-path scheduling tools built for the master schedule. 3WLA doesn't replace them. It's for the short-term plan the field works from: the 3-week look-ahead. Here's how the two fit together.

    Updated 13 November 2026 · 5 min read

    Different jobs

    Master schedule tools compared with 3WLA
    TopicMaster schedule (P6, Microsoft Project)3-week look-ahead (3WLA)
    PurposeWhole project, contract dates, critical pathThe next 21 days of field work
    Owned byScheduler, project controls or PMSuperintendent with the foremen
    Level of detailActivities across the whole jobTasks of a few days, by area and trade
    UpdatedUsually monthly, or as the contract requiresEvery week
    LogicRelationships, float, resources, baselinesDates, trade commitments, constraints
    Who works in itTrained schedulers with a paid licence eachAnyone on the project; viewers just open a link
    Who reads itOwner, PM, project controlsField team, subcontractors, inspectors

    Why not run the look-ahead in P6?

    You can filter a three-week window in P6 or Microsoft Project and print it, and many teams do. It works until the field needs more detail than the master schedule should carry.

    Foremen rarely have access to the scheduling tool. Breaking activities down by area, crew and day clutters the master schedule's logic. And weekly field changes shouldn't rewrite the schedule the contract is measured against. Keeping the look-ahead separate lets the field plan in detail while the master schedule stays clean.

    Keeping the two in line

    1. Export the master schedule to PDF

      From Primavera P6, Microsoft Project, Procore or similar.

    2. Upload it to an AI comparison

      On the Business plan, 3WLA reads the activities and dates and lists what is on track, moved, early or missing from your look-ahead (with a 2-day tolerance).

    3. Review and adjust

      The comparison is advisory. Decide what to change in the look-ahead, and what to raise with the scheduler.

    4. Feed it back

      Pass real field progress and slips to whoever updates the master schedule each month.

    What 3WLA doesn't do

    Keep those in your master schedule tool. 3WLA is the field's working plan next to it.

    • Critical path logic, relationships and float.
    • Resource levelling or cost loading.
    • Baselines for contract schedule submissions.

    Common questions

    Can 3WLA import a P6 XER or Microsoft Project file?

    Not directly. Export the activities you need to Excel and paste them into the grid, or upload a PDF export for an AI comparison.

    Which plan includes AI comparison?

    Business, with 50 comparisons a month. Failed comparisons aren't counted.

    Do we need a scheduler to use 3WLA?

    No. It's built for superintendents and project managers. If you can fill in a spreadsheet, you can build a look-ahead.